8880 NorthStar Entergy Vermont Yankee Transfer Open Case Age: 432
Regulatory / Petition: New Paper Filing 12/16/16
Commissioner  
NorthStar Decommissioning Holdings, LLC [Petitioner]  
Electric
3 Issue(s):Financing § 108    
Schedule-Portal
Hearing/Events 
Date/Times Description Location Event
Status
Board
Personnel
Result Result
Date
Event End
Date/Time
  Petition
    February 23, 2018 1:30 PM Status Conference Susan M. Hudson Hearing Room Noticed Commissioner Commissioner Lead Staff Team Member Staff Team Member Staff Team Member Staff Team Member
    April 6, 2017 7:00 PM Public Hearing Noticed Commissioner Commissioner Lead Staff Team Member Staff Team Member Staff Team Member Held 04/06/2017
    April 6, 2017 6:00 PM Project Information Presentation Noticed Commissioner Commissioner Lead Staff Team Member Staff Team Member Staff Team Member Held 04/06/2017
    February 1, 2017 11:00 AM Prehearing Conference Susan M. Hudson Hearing Room Noticed Commissioner Commissioner Lead Staff Team Member Staff Team Member Staff Team Member Held 02/01/2017
Case Schedule 
Due Date Name Related to Filed by
03/02/2018
Response to Motion Due Date
02/16/18 Motion - Other
NorthStar Group Services, Inc. [PET], Vermont Agency of Natural Resources [P], Vermont Office of the Attorney General [PART], Vermont Department of Public Service [P], Vermont Office of the Attorney General [P], LVI Parent Corp. [PET], Elnu Abenaki Tribe [P], NorthStar Group Holdings, LLC [PET], Conservation Law Foundation [P], Town of Vernon Planning and Economic Development Commission [P], Entergy Nuclear Operations, Inc. [PET], Entergy Nuclear Vermont Investment Company, LLC [PET], NorthStar Decommissioning Holdings, LLC [PET], NorthStar Nuclear Decommissioning Company, LLC [PET], Windham Regional Commission [P], New England Coalition on Nuclear Pollution, Inc. [P]
03/01/2018
Response to Motion Due Date
02/15/18 Motion - Other
Conservation Law Foundation [P]
02/20/2018
Response to Motion Due Date
02/5/18 Motion - Other
Vermont Department of Public Service [P]
02/08/2018
Response to Motion Due Date
01/25/18 Motion - Other
NorthStar Group Services, Inc. [PET], NorthStar Decommissioning Holdings, LLC [PET], NorthStar Nuclear Decommissioning Company, LLC [PET], NorthStar Group Holdings, LLC [PET]
02/02/2018
Response to Motion Due Date
01/19/18 Motion - Other
NorthStar Group Services, Inc. [PET], Entergy Nuclear Operations, Inc. [PET], Entergy Nuclear Vermont Investment Company, LLC [PET], LVI Parent Corp. [PET], NorthStar Decommissioning Holdings, LLC [PET], NorthStar Nuclear Decommissioning Company, LLC [PET], NorthStar Group Holdings, LLC [PET]
02/01/2018
Response to Motion Due Date
01/18/18 Motion - Reconsideration
NorthStar Group Services, Inc. [PET], NorthStar Decommissioning Holdings, LLC [PET], NorthStar Nuclear Decommissioning Company, LLC [PET], NorthStar Group Holdings, LLC [PET]
01/26/2018
Response to Motion Due Date
01/12/18 Motion - Other
NorthStar Group Services, Inc. [PET], Entergy Nuclear Operations, Inc. [PET], Entergy Nuclear Vermont Investment Company, LLC [PET], LVI Parent Corp. [PET], NorthStar Decommissioning Holdings, LLC [PET], NorthStar Nuclear Decommissioning Company, LLC [PET], NorthStar Group Holdings, LLC [PET]
01/26/2018
Response to Motion Due Date
01/12/18 Motion - Other
NorthStar Group Services, Inc. [PET], LVI Parent Corp. [PET], NorthStar Decommissioning Holdings, LLC [PET], NorthStar Nuclear Decommissioning Company, LLC [PET], NorthStar Group Holdings, LLC [PET]
01/25/2018
Response to Motion Due Date
01/11/18 Motion - Other
Vermont Department of Public Service [P]
01/18/2018
Depositions 1/8 to 1/18/2018
8880
01/18/2018
Due Date for Party Comments
Memorandum Requesting Comments
Board Issued
01/12/2018
Response to Motion Due Date
12/28/17 Motion - Other
NorthStar Group Services, Inc. [PET], Entergy Nuclear Operations, Inc. [PET], Entergy Nuclear Vermont Investment Company, LLC [PET], LVI Parent Corp. [PET], NorthStar Decommissioning Holdings, LLC [PET], NorthStar Nuclear Decommissioning Company, LLC [PET], NorthStar Group Holdings, LLC [PET]
12/22/2017
Responses to sur-rebuttal discovery requests due
8880
12/15/2017
Deposition notices due
8880
12/15/2017
Response to Motion Due Date
11/30/17 Motion - Other
NorthStar Group Services, Inc. [PET], Entergy Nuclear Operations, Inc. [PET], Entergy Nuclear Vermont Investment Company, LLC [PET], LVI Parent Corp. [PET], NorthStar Decommissioning Holdings, LLC [PET], NorthStar Group Holdings, LLC [PET]
12/08/2017
Deadline for sur-rebuttal discovery requests
8880
12/05/2017
Response to Motion Due Date
11/20/17 Motion - Other
Entergy Nuclear Operations, Inc. [PET], Entergy Nuclear Vermont Investment Company, LLC [PET]
12/01/2017
Non-petitioners file sur-rebutal testimony
8880
11/28/2017
Petitioners' responses to rebuttal discovery requests due
8880
11/24/2017
Response to Motion Due Date
11/8/17 Motion - Other
Entergy Nuclear Operations, Inc. [PET], Entergy Nuclear Vermont Investment Company, LLC [PET]
11/24/2017
Response to Motion Due Date
11/8/17 Motion - Other
Entergy Nuclear Operations, Inc. [PET], Entergy Nuclear Vermont Investment Company, LLC [PET]
11/17/2017
Response to Motion Due Date
11/2/17 Motion - Other
NorthStar Group Services, Inc. [PET], Entergy Nuclear Operations, Inc. [PET], Entergy Nuclear Vermont Investment Company, LLC [PET], LVI Parent Corp. [PET], NorthStar Decommissioning Holdings, LLC [PET], NorthStar Nuclear Decommissioning Company, LLC [PET], NorthStar Group Holdings, LLC [PET]
11/07/2017
Response to Motion Due Date
10/23/17 Motion - Other
New England Coalition on Nuclear Pollution, Inc. [P]
10/31/2017
Response to Motion Due Date
10/16/17 Motion - Withdraw as Representative
NorthStar Decommissioning Holdings, LLC [PET]
10/30/2017
Deadline for rebuttal discovery requests on petitioners
8880
10/25/2017
Response to Motion Due Date
10/10/17 Motion - Other
New England Coalition on Nuclear Pollution, Inc. [P]
10/23/2017
Response to Motion Due Date
09/29/17 Motion - Other
NorthStar Group Services, Inc. [PET], Entergy Nuclear Operations, Inc. [PET], Entergy Nuclear Vermont Investment Company, LLC [PET], LVI Parent Corp. [PET], NorthStar Decommissioning Holdings, LLC [PET], NorthStar Nuclear Decommissioning Company, LLC [PET], NorthStar Group Holdings, LLC [PET]
10/17/2017
Petitioners pre-file rebuttal testimony
8880
10/13/2017
Depositions 10/2 to 10/13/2017
8880
10/09/2017
Response to Motion Due Date
09/22/17 Motion - Pro Hac Vice
Vermont Department of Public Service [P]
10/09/2017
Response to Motion Due Date
09/22/17 Motion - Pro Hac Vice
Vermont Department of Public Service [P]
10/09/2017
Response to Motion Due Date
09/22/17 Motion - Pro Hac Vice
Vermont Department of Public Service [P]
10/06/2017
Responses to petitioners’ 1st round of discovery requests by NEC due
8880
09/27/2017
Responses to petitioners’ 1st round of discovery requests by all non-petitioners other than NEC due due
8880
09/20/2017
Deadline for petitioners' 1st round of discovery requests on the Town
8880
09/14/2017
Deposition notices due
8880
09/13/2017
Response to Motion Due Date
08/29/17 Motion - Confidential Designation
NorthStar Group Services, Inc. [PET], Entergy Nuclear Operations, Inc. [PET], Entergy Nuclear Vermont Investment Company, LLC [PET], LVI Parent Corp. [PET], NorthStar Decommissioning Holdings, LLC [PET], NorthStar Nuclear Decommissioning Company, LLC [PET], NorthStar Group Holdings, LLC [PET]
09/13/2017
Town pre-files initial testimony
8880
09/07/2017
Deadline for petitioners’ 1st round of discovery requests
8880
08/30/2017
Non-petitioner parties pre-file initial testimony
8880
08/14/2017
Response to Motion Due Date
07/28/17 Motion - Change Schedule
Town of Vernon Planning and Economic Development Commission [P]
08/03/2017
Response to Motion Due Date
07/19/17 Motion - Change Schedule
NorthStar Group Services, Inc. [PET], Entergy Nuclear Operations, Inc. [PET], Entergy Nuclear Vermont Investment Company, LLC [PET], LVI Parent Corp. [PET], NorthStar Decommissioning Holdings, LLC [PET], NorthStar Nuclear Decommissioning Company, LLC [PET], NorthStar Group Holdings, LLC [PET]
08/03/2017
Petitioners’ responses on DM/PIDS Discovery Requests due
8880
07/21/2017
Petitioners' responses to 2nd round of discovery requests due
8880
07/21/2017
Deadline for Deal Model/Pay Item Disbursement Schedule (“DM/PIDS”) discovery requests on petitioners
8880
07/10/2017
Response to Motion Due Date
06/23/17 Motion - Other
Vermont Office of the Attorney General [PART], Vermont Department of Public Service [P], Vermont Agency of Natural Resources [PART]
07/06/2017
Response to Motion Due Date
06/21/17 Motion - Withdraw as Representative
Vermont Department of Public Service [P]
06/29/2017
Response to Motion Due Date
06/14/17 Motion - Pro Hac Vice
Scholze, Ingrid Esq. [REP]
06/26/2017
Response to Motion Due Date
06/9/17 Motion - Withdraw as Representative
Entergy Nuclear Operations, Inc. [PET], Entergy Nuclear Vermont Investment Company, LLC [PET]
06/22/2017
Deadline for 2nd round of discovery requests on petitioners
8880
06/21/2017
Response to Motion Due Date
06/6/17 Motion - Other
New England Coalition on Nuclear Pollution, Inc. [P]
06/20/2017
Response to Motion Due Date
06/5/17 Motion - Withdraw as Representative
Vermont Department of Public Service [P]
06/05/2017
Response to Motion Summary Judgement Due Date
05/5/17 Motion - Summary Judgment
New England Coalition on Nuclear Pollution, Inc. [P]
05/26/2017
Response to Motion Due Date
05/11/17 Motion - Other
Vermont Department of Public Service [P]
05/26/2017
Response to Motion Due Date
05/11/17 Motion - Other
Vermont Department of Public Service [P], Vermont Agency of Natural Resources [PART]
05/22/2017
Response to Motion Due Date
05/5/17 Motion - Confidential Designation
NorthStar Decommissioning Holdings, LLC [PET]
05/17/2017
Response to Motion Due Date
05/2/17 Motion - Other
Vermont Department of Public Service [P]
04/26/2017
Petitioners' responses to 1st round of discovery requests due
8880
04/25/2017
Response to Motion Due Date
04/10/17 Motion - Change Schedule
NorthStar Group Services, Inc. [PET], Entergy Nuclear Operations, Inc. [PET], Entergy Nuclear Vermont Investment Company, LLC [PET], LVI Parent Corp. [PET], NorthStar Decommissioning Holdings, LLC [PET], NorthStar Nuclear Decommissioning Company, LLC [PET], NorthStar Group Holdings, LLC [PET]
04/13/2017
Response to Motion Due Date
03/29/17 Motion - Change Schedule
NorthStar Group Services, Inc. [PET], Entergy Nuclear Operations, Inc. [PET], Entergy Nuclear Vermont Investment Company, LLC [PET], LVI Parent Corp. [PET], NorthStar Decommissioning Holdings, LLC [PET], NorthStar Nuclear Decommissioning Company, LLC [PET], NorthStar Group Holdings, LLC [PET]
03/28/2017
Response to Motion Due Date
03/13/17 Motion to Intervene
Abenaki Nation of Missisquoi [P]
03/23/2017
Response to Motion Due Date
03/8/17 Motion to Intervene
Elnu Abenaki Tribe [P]
03/17/2017
Deadline for 1st round of discovery requests on petitioners
8880
03/16/2017
Response to Motion Due Date
03/1/17 Motion to Intervene
Town of Vernon Planning and Economic Development Commission [P]
03/16/2017
Response to Motion Due Date
03/1/17 Motion to Intervene
Vermont Agency of Natural Resources [P]
03/16/2017
Response to Motion Due Date
03/1/17 Motion to Intervene
Associated Industries of Vermont [P]
03/16/2017
Response to Motion Due Date
03/1/17 Motion to Intervene
Vermont Office of the Attorney General [P]
03/10/2017
Deadline for any objections to prefiled testimony of petitioners
8880
03/08/2017
Response to Motion Due Date
02/20/17 Motion to Intervene
03/08/2017
Response to Motion Due Date
02/20/17 Motion to Intervene
International Brotherhood of Electrical Workers, Local 300 [P]
03/06/2017
Response to Motion Due Date
02/3/17 Motion to Intervene
Windham Regional Commission [P]
03/06/2017
Responses to motions to intervene
8880
03/01/2017
Deadline for timely motions to intervene
8880
03/01/2017
Response to Motion Due Date
02/14/17 Motion to Intervene
Conservation Law Foundation [P]
02/13/2017
Response to Motion Due Date
01/27/17 Motion to Intervene
New England Coalition on Nuclear Pollution, Inc. [P]
02/13/2017
Responses to motion to intervene of New England Coaltion
8880
02/01/2017
Response to Motion Due Date
02/1/17 Motion - Pro Hac Vice
Vermont Department of Public Service [P]
02/01/2017
Response to Motion Due Date
02/1/17 Motion - Pro Hac Vice
Vermont Department of Public Service [P]
02/01/2017
Response to Motion Due Date
02/1/17 Motion - Pro Hac Vice
Vermont Department of Public Service [P]
01/03/2017
Response to Motion Due Date
01/03/2017
Response to Motion Due Date
12/16/16 Motion - Pro Hac Vice
Entergy Nuclear Vermont Investment Company, LLC [PET]
01/03/2017
Response to Motion Due Date
12/16/16 Motion - Pro Hac Vice
Entergy Nuclear Vermont Investment Company, LLC [PET]
01/03/2017
Response to Motion Due Date
12/16/16 Motion - Pro Hac Vice
Entergy Nuclear Vermont Investment Company, LLC [PET]
Print this Page